JWB Inc., dba AR Homes of Southeast NC
JWB Inc., dba AR Homes of Southeast NC has filed 22 building permits in Wilmington since 2021, closing 91% of 22 rated permits. 2 permits remain open. 8.8 points below the city median of 99.7%. Busiest year: 2023 with 13 permits.
91%
22
Construction Permits
2
Currently Open
22
Rate-Eligible
permits > 1yr old
2021–2024
Years Active
Closure rate based on permits older than 1 year. "Issued" and "Stop Work" statuses are excluded.
Project Financials
$8.7M
Total Declared Value
$456K
Avg per Permit
$576K
Largest Project
Based on 19 of 22 construction permits with declared valuation data.
Year-by-Year Summary
2024
100.0%
Open0
Closed2
2 closed / 2 rated
2023
84.6%
Open2
Closed11
11 closed / 13 rated
2022
100.0%
Open0
Closed3
3 closed / 3 rated
2021
100.0%
Open0
Closed4
4 closed / 4 rated
All Permits
22 permits
| Status | Permit # | Address | Issued▼ | |||
|---|---|---|---|---|---|---|
| Closed | Mechanical | 262 TRISAIL TER, Wilmington | Feb 8, 2024 | Oct 3, 2024 | $369,912.66 | |
| Closed | Mechanical | 262 TRISAIL TER, Wilmington | Jan 30, 2024 | Dec 3, 2024 | $369,912.66 | |
| Closed | Electrical | 262 TRISAIL TER, Wilmington | Dec 6, 2023 | Oct 4, 2024 | $0 | |
| Closed | Electrical | 4002 DAUNTLESS LN, Wilmington | Nov 29, 2023 | Aug 26, 2024 | $482,187.88 | |
| Closed | Electrical | 4008 DAUNTLESS LN, Wilmington | Oct 24, 2023 | Jul 1, 2024 | $469,504.53 | |
| Closed | Plumbing | 4002 DAUNTLESS LN, Wilmington | Oct 23, 2023 | Aug 12, 2024 | $482,187.88 | |
| Closed | Mechanical | 4002 DAUNTLESS LN, Wilmington | Sep 29, 2023 | Aug 1, 2024 | $482,187.88 | |
| Closed | Mechanical | 4002 DAUNTLESS LN, Wilmington | Sep 21, 2023 | Aug 8, 2024 | $482,187.88 | |
| Open | Electrical | 3610 WATERCRAFT FERRY AV, Wilmington | Sep 15, 2023 | — | $509,429.51 | |
| Closed | Mechanical | 3610 WATERCRAFT FERRY AV, Wilmington | Jun 22, 2023 | Jul 15, 2025 | $20,000 | |
| Open | Electrical | 3610 WATERCRAFT FERRY AV, Wilmington | Jun 16, 2023 | — | $0 | |
| Closed | Plumbing | 4002 DAUNTLESS LN, Wilmington | Jun 7, 2023 | Oct 20, 2023 | $482,187.88 | |
| Closed | Mechanical | 4020 DAUNTLESS LN, Wilmington | May 26, 2023 | Feb 2, 2024 | $566,670.02 | |
| Closed | Electrical | 4020 DAUNTLESS LN, Wilmington | May 2, 2023 | Feb 5, 2024 | $566,670.02 | |
| Closed | Mechanical | 4020 DAUNTLESS LN, Wilmington | Mar 21, 2023 | Jan 12, 2024 | $0 | |
| Closed | Plumbing | 4020 DAUNTLESS LN, Wilmington | Oct 13, 2022 | Feb 7, 2024 | $566,670.02 | |
| Closed | Plumbing | 3516 WATERCRAFT FERRY AV, Wilmington | Jul 11, 2022 | Nov 30, 2023 | $303,959.24 | |
| Closed | Plumbing | 3610 WATERCRAFT FERRY AV, Wilmington | Jul 1, 2022 | Jul 15, 2025 | $509,429.51 | |
| Closed | Plumbing | 524 EDGERTON DR, Wilmington | Jul 30, 2021 | Nov 1, 2021 | $426,601.72 | |
| Closed | Plumbing | 4013 DAUNTLESS LN, Wilmington | Jul 28, 2021 | Mar 8, 2022 | $575,824.09 | |
| Closed | Electrical | 4024 DAUNTLESS LN, Wilmington | Jul 12, 2021 | Sep 21, 2022 | $572,735.97 | |
| Closed | Electrical | 524 EDGERTON DR, Wilmington | Apr 12, 2021 | Nov 3, 2021 | $426,601.72 |