SOUND CUSTOM BUILDERS LLC has filed 57 building permits in Wilmington since 2020, closing 100% of 45 rated permits. 8 permits remain open. Primarily files building permits. 0.3 points above the city median of 99.7%. Busiest year: 2021 with 13 permits.
Closure rate based on permits older than 1 year. "Issued" and "Stop Work" statuses are excluded.
Project Financials
Based on 52 of 57 construction permits with declared valuation data.
Performance by Permit Type
100.0% closed vs 99% median, 1.5 points higher
100.0% closed vs 89% median, 11.3 points higher
Median based on all applicants with 20+ rated permits in each category. Only permits older than 1 year are rated.
Year-by-Year Summary
2026(YTD)
Too early to rate — permits need 1 year to mature
2025
2 closed / 2 rated
2024
7 closed / 7 rated
2023
12 closed / 12 rated
2022
9 closed / 9 rated
2021
13 closed / 13 rated
2020
2 closed / 2 rated
All Permits
| Status | Permit # | Address | Issued▼ | |||
|---|---|---|---|---|---|---|
| Open | Mechanical | 807 JOHNS ORCHARD LN, Wilmington | May 28, 2026<1yr | — | $0 | |
| Open | Electrical | 807 JOHNS ORCHARD LN, Wilmington | May 18, 2026<1yr | — | $0 | |
| Open | Plumbing | 807 JOHNS ORCHARD LN, Wilmington | May 18, 2026<1yr | — | $0 | |
| Open | Building | 807 JOHNS ORCHARD LN, Wilmington | May 13, 2026<1yr | — | $0 | |
| Open | Mechanical | 5304 HANAHAN DR, Wilmington | Mar 11, 2026<1yr | — | $110,290 | |
| Open | Plumbing | 5304 HANAHAN DR, Wilmington | Mar 3, 2026<1yr | — | $110,290 | |
| Open | Building | 5304 HANAHAN DR, Wilmington | Feb 11, 2026<1yr | — | $110,290 | |
| Closed | Electrical | 1944 DEEP CREEK RUN, Wilmington | Nov 21, 2025<1yr | Jan 14, 2026 | $46,762.96 | |
| Closed | Plumbing | 1944 DEEP CREEK RUN, Wilmington | Nov 19, 2025<1yr | Jan 12, 2026 | $46,762.96 | |
| Closed | Mechanical | 1944 DEEP CREEK RUN, Wilmington | Oct 31, 2025<1yr | Jan 12, 2026 | $46,762.96 | |
| Closed | Building | 1944 DEEP CREEK RUN, Wilmington | Oct 21, 2025<1yr | Jan 21, 2026 | $46,762.96 | |
| Open | Building | 807 JOHNS ORCHARD LN, Wilmington | Jun 11, 2025<1yr | — | $669,570.59 | |
| Closed | Building | 1142 JEANELLE MOORE BLVD, Wilmington | May 23, 2025 | Mar 27, 2026 | $333,406.67 | |
| Closed | Building | 1142 JEANELLE MOORE BLVD, Wilmington | May 23, 2025 | Mar 16, 2026 | $333,406.67 | |
| Closed | Plumbing | 7915 SANDERLING PL, Wilmington | Nov 4, 2024 | Jan 28, 2025 | $28,013.66 | |
| Closed | Building | 7915 SANDERLING PL, Wilmington | Oct 23, 2024 | Jan 29, 2025 | $28,013.66 | |
| Closed | Building | 8029 BALD EAGLE LN, Wilmington | Sep 9, 2024 | Apr 30, 2025 | $55,145 | |
| Closed | Mechanical | 1049 SUMMER WIND DR, Wilmington | May 22, 2024 | May 24, 2024 | $28,675.4 | |
| Closed | Building | 1049 SUMMER WIND DR, Wilmington | Apr 5, 2024 | May 31, 2024 | $28,675.4 | |
| Closed | Plumbing | 2007 DEEP CREEK RUN, Wilmington | Jan 29, 2024 | Jul 9, 2024 | $74,997.2 | |
| Closed | Building | 2007 DEEP CREEK RUN, Wilmington | Jan 2, 2024 | Jul 25, 2024 | $74,997.2 | |
| Closed | Electrical | 7413 NAUTICA YACHT CLUB DR, Wilmington | Dec 12, 2023 | Apr 2, 2024 | $84,702.72 | |
| Closed | Mechanical | 7413 NAUTICA YACHT CLUB DR, Wilmington | Dec 5, 2023 | Mar 26, 2024 | $84,702.72 | |
| Closed | Electrical | 7426 NAUTICA YACHT CLUB DR, Wilmington | Nov 21, 2023 | Nov 22, 2023 | $604,609.78 | |
| Closed | Electrical | 8504 BALD EAGLE LN, Wilmington | Nov 21, 2023 | Nov 22, 2023 | $1,026,027.87 | |
| Closed | Building | 8909 CHAMPION HILLS DR, Wilmington | Nov 20, 2023 | May 23, 2024 | $110,290 | |
| Closed | Plumbing | 7413 NAUTICA YACHT CLUB DR, Wilmington | Nov 13, 2023 | Mar 26, 2024 | $84,702.72 | |
| Closed | Building | 7430 POSEIDON PT, Wilmington | Nov 6, 2023 | Nov 12, 2024 | $525,642.14 | |
| Closed | Building | 7413 NAUTICA YACHT CLUB DR, Wilmington | Sep 21, 2023 | Apr 22, 2024 | $84,702.72 | |
| Closed | Building | 7431 POSEIDON PT, Wilmington | Jul 20, 2023 | Oct 17, 2024 | $557,626.24 | |
| Closed | Mechanical | 8504 BALD EAGLE LN, Wilmington | Apr 6, 2023 | May 16, 2024 | $1,026,027.87 | |
| Closed | Building | 7426 NAUTICA YACHT CLUB DR, Wilmington | Mar 10, 2023 | Jun 5, 2024 | $604,609.78 | |
| Closed | Electrical | 7410 LUCKY FISH LN, Wilmington | Feb 13, 2023 | Feb 17, 2023 | $717,215.87 | |
| Closed | Building | 8504 BALD EAGLE LN, Wilmington | Oct 31, 2022 | May 23, 2024 | $1,026,027.87 | |
| Closed | Mechanical | 7410 LUCKY FISH LN, Wilmington | Sep 26, 2022 | May 16, 2023 | $717,215.87 | |
| Closed | Mechanical | 7410 LUCKY FISH LN, Wilmington | Aug 31, 2022 | May 22, 2023 | $717,215.87 | |
| Closed | Mechanical | 7410 LUCKY FISH LN, Wilmington | Aug 30, 2022 | May 24, 2023 | $717,215.87 | |
| Closed | Mechanical | 8712 BALD EAGLE LN, Wilmington | Jul 25, 2022 | Sep 29, 2022 | $824,086.88 | |
| Closed | Electrical | 8712 BALD EAGLE LN, Wilmington | Jul 11, 2022 | Jul 12, 2022 | $824,086.88 | |
| Closed | Plumbing | 7410 LUCKY FISH LN, Wilmington | Apr 27, 2022 | May 23, 2023 | $717,215.87 | |
| Closed | Electrical | 7410 LUCKY FISH LN, Wilmington | Apr 4, 2022 | May 17, 2023 | $717,215.87 | |
| Closed | Building | 7410 LUCKY FISH LN, Wilmington | Apr 4, 2022 | Jun 2, 2023 | $717,215.87 | |
| Closed | Mechanical | 8712 BALD EAGLE LN, Wilmington | Nov 22, 2021 | Oct 14, 2022 | $824,086.88 | |
| Closed | Electrical | 1824 MIDDLE SOUND LOOP RD, Wilmington | Nov 16, 2021 | Nov 19, 2021 | $516,157.2 | |
| Closed | Mechanical | 1824 MIDDLE SOUND LOOP RD, Wilmington | Sep 8, 2021 | Dec 20, 2021 | $516,157.2 | |
| Closed | Mechanical | 1824 MIDDLE SOUND LOOP RD, Wilmington | Jul 26, 2021 | Dec 14, 2021 | $516,157.2 | |
| Closed | Mechanical | 1824 MIDDLE SOUND LOOP RD, Wilmington | Jul 15, 2021 | Dec 15, 2021 | $516,157.2 | |
| Closed | Mechanical | 1206 HELLENE DR, Wilmington | Apr 9, 2021 | Apr 16, 2021 | $514,171.98 | |
| Closed | Plumbing | 1824 MIDDLE SOUND LOOP RD, Wilmington | Apr 8, 2021 | Dec 14, 2021 | $20,000 | |
| Closed | Plumbing | 8712 BALD EAGLE LN, Wilmington | Apr 7, 2021 | Oct 12, 2022 | $25,000 |